|  | Multi-Leveled - Rail Road Tie Walls and Steps
 
 1989: Multi-Leveled - Rail Road Tie Walls and Steps 
Huntington, New York
 ITEM- RRT - 05
 
 
Stage 1 - Property Plan and site survey.Stage 2 - Site preparation to include removal of old; stairs,  trees and brush  with our Bobcat.  Complete Demolition of all old wall structures. Latter all  debris was hauled to land fill and discarded.Stage 3 - Brick on sand was installed on each step and landing here.Stage 4 - Bobcat used to backfill behind all walls after construction was completed. Mult-Teared construction due to extreme incline of terrain. All timbers used were; 30 year cca, grade 1, pressure treated lumber. |  |